Bathroom Renewal
Orbit Housing

Mossvale were responsible for the installation of new bathrooms to Orbit Housing properties within the West Midlands via Bullocks.  94 bathrooms were insalled within a 6 month period.

Scope of works included but were not limited to:

  • Bathroom suite replacement including electrics, plastering, wall and floor finishes
  • New windows and doors
  • Gas heating including boiler relocation, radiator relocation and heating flush and clean

Customer liaison support was via Bullock’s but our Site Delivery Team are extremely experienced in working in occupied properties and ensure that the residents needs are at the forefront of all works conducted.

Profile

 

Client

Orbit Housing Association via Bullock Construction Ltd
 

Value

£100,000

 

Start Date

October 2013

 

Finish Date

June 2014